Welland Campus Spring Power Shutdown
From April 30 to May 3, 2026, Niagara College’s Welland Campus will be closed for major upgrades to the electrical infrastructure to increase capacity and improve operational resilience.
These scheduled upgrades support our Sustainability Plan and carbon reduction goals, supporting long-term operational and environmental priorities, as well as the new Health Education Building and future campus projects.
The dates – between Winter-and-Spring Term – were carefully selected in consultation with academic departments to minimize disruption, and contractor availability.
To ensure everyone’s safety, access to campus will be unavailable while the work is being completed. Please note that campus doors will be locked and there will be limited exterior power and lighting in campus parking lots.
- Please take any materials or belongings you need before the closure begins on April 30.
- Students should check Brightspace for program-specific information about adjustments to academic programming during this time. WC support services may be available via alternate delivery, and students can continue to access in-person support and services at the Daniel J. Patterson Campus in Niagara-on-the-Lake.
- Remote work will continue for WC employees, and the Daniel J. Patterson Campus in Niagara-on-the-Lake is unaffected and will remain open.
The college will be closed starting at 12:00 a.m. on April 30 until May 3, 2026.
- Simcoe, Secord, Merritt, Voyager, Applied Health, Athletics, Residences, Black Walnut, Pavilion, WAMIC/Rankin, McKenzie, A Child’s World (ACW).
- ACW and Residence will be running on temporary power, so they will remain largely unaffected.
Frequently Asked Questions (FAQ)
Access to Welland Campus will be unavailable while the electrical work is being completed to ensure everyone’s safety. Campus doors will be locked and there will be limited exterior power and lighting in campus parking lots.
The Daniel J. Patterson Campus in Niagara-on-the-Lake is unimpacted and will remain open.
Yes. The Daniel. J Patterson Campus will remain open and is unaffected by the shutdown.
No. Doors to Welland Campus will be locked from April 30 to May 3. You are encouraged to take any materials or belongings you need before the closure.
Simcoe, Secord, Merritt, Voyager, Applied Health, Athletics, Residences, Black Walnut, Pavilion, WAMIC/Rankin, McKenzie, A Child’s World (ACW).
Exterior power and lighting will be limited in campus parking lots.
No. The fitness centre at the Welland Campus will be closed.
Regular hours of operation continue at the fitness centre at the Daniel. J Patterson Campus in Niagara-on-the-Lake.
Visit NC Fitness CentreNo. Welland Food Services will be closed during the duration of the shutdown.
- Save all open files and power down your workstations. Turn off computers, monitors, and peripherals instead of leaving them in sleep or standby mode.
- Lab instruments should be properly shut down according to manufacturers’ instructions to avoid damage. Emergency generators will be used in critical areas of campus only.
- Ensure critical lab freezers or refrigerators have enough coolant or backup power if they must stay on.
- Maintain a list of systems and equipment to power back up first once power resumes.
- Coordinate with team members to monitor critical systems if necessary.
Friendly NC staff are here to answer your questions. Chat with us, or contact us via email or phone.